Home › Guides › How Do Fence Companies Price a Fence Job?
How Do Fence Companies Price a Fence Job?
Short answer: Fence companies price a job by adding four things: materials for the run, crew hours at your full labor cost, a share of overhead, and profit. Then they divide by the linear feet to get a per foot price and add gates, removal and hard digging as separate lines. The right number depends on your costs, not a rival's.
- A fence price is materials plus loaded labor plus overhead plus profit, then divided by linear feet.
- Price gates, old fence removal, rock and slope as their own lines, not inside the per foot rate.
- Margin and markup are different: a 30% markup on cost gives only about a 23% margin.
- Private construction employers paid an average of $51.96 per hour worked in total compensation in June 2026.
- Fence installs are on the list of digging jobs where you contact 811 a few business days first.
- If you are self-employed, the IRS self-employment tax rate is 15.3%, so build it into your pay.
Most fence companies start by copying the per foot number they hear around town. That works until a job with rocky ground, three gates and a slope eats the whole profit. This guide shows how to build a price from your own costs, so every bid covers the work and pays you.
What goes into a fence price?
Every fence bid has the same four layers. Get each one right and the per foot number takes care of itself.
| Layer | What it covers on a fence job | Where the number comes from |
|---|---|---|
| Materials | Posts, rails, pickets or panels, concrete, hardware, gate kits, caps | Your supplier quote for this run, plus waste |
| Labor | Layout, digging, setting posts, hanging panels, gates, cleanup | Crew hours times your full cost per hour |
| Overhead | Truck, trailer, auger, insurance, office, phone, software, marketing | Your yearly overhead spread across crew hours |
| Profit | What the business keeps after every bill is paid | A target margin you pick and stick to |
Skip any layer and you are working for less than you think. The one most owners skip is overhead. The truck payment and the insurance bill do not care how many feet you set this month.
What is the difference between markup and margin?
Markup is the percent you add on top of your cost. Margin is the percent of the final price that is profit. They are not the same number, and mixing them up is an easy way to underprice a fence.
Here is the math with a $10,000 job cost (example numbers):
| You add | Price | Profit | Margin |
|---|---|---|---|
| 20% markup | $12,000 | $2,000 | 16.7% |
| 30% markup | $13,000 | $3,000 | 23.1% |
| 50% markup | $15,000 | $5,000 | 33.3% |
If you want a 30% margin, do not add 30%. Divide your cost by 0.70 instead. $10,000 divided by 0.70 is about $14,286. That is the price that leaves 30% of the money in your pocket after costs.
How do you work out your real labor cost per hour?
Your labor cost is more than the wage you pay. Payroll taxes, workers comp, paid time off and any benefits all sit on top. The Bureau of Labor Statistics tracks this. In June 2026, private employers in the construction industry paid an average of $51.96 per hour worked in total compensation. Of that, $36.13 was wages and $15.84 was benefits (BLS: Employer Costs for Employee Compensation, Table 4 (2026)). Across all private industry, benefits were 30.0% of compensation costs (BLS: Employer Costs for Employee Compensation news release (2026)).
Those are national averages across all of construction, not fence crews. Use them as a check, not as your number. To get your own:
- Add up a year of crew wages.
- Add payroll taxes, workers comp, and any health or retirement costs.
- Divide by the hours your crew actually spends on job sites.
That last part matters. A crew paid for 40 hours that spends 6 of them driving to the yard and loading the trailer has 34 job hours. Your rate has to cover the 6.
If you are a one-truck owner who installs too, pay yourself on paper. The IRS says the self-employment tax rate is 15.3%: 12.4% for Social Security and 2.9% for Medicare (IRS: Self-employment tax (2026)). If you leave that out, your hourly cost is too low.
How do you price fence materials?
Price materials from a current supplier quote for this exact run, not last spring's sheet. Lumber, vinyl and aluminum prices move, and fence bids often sit for weeks before the homeowner signs.
Count these pieces for each run:
- Line posts at your spacing, plus corner, end and gate posts, which are often heavier.
- Rails and pickets, or panels for vinyl and aluminum.
- Concrete by the bag per post hole, more for gate posts.
- Hardware: brackets, screws, hinges, latches, drop rods, post caps.
- Gate kits priced one by one.
- Waste: cut-offs and a few spare pickets. Pick a waste percent from your past jobs.
Write an expiry date on the quote, such as 30 days. That protects you if the supplier raises prices before the homeowner signs.
How do you build a fence price step by step?
Step 1: Measure and draw the run
Walk the line with the homeowner. Mark corners, ends, gates and slope. Note what is under the line: roots, rock, sprinkler lines, an old fence. Fence installs are one of the digging jobs where you should contact 811 a few business days before you start, and the service is free (811: Before you dig). Add that lead time to your schedule.
Step 2: List materials and get the supplier price
Build the materials list from your drawing. Add your waste percent. Use the supplier price for this week.
Step 3: Estimate crew hours
Break the job into tasks: removal, layout, holes, setting posts, cure time, rails and pickets or panels, gates, cleanup. Use your own past jobs for the hours. If you do not track hours yet, start now. It is the single best way to price better next season.
Step 4: Add job costs
Dump fees for an old fence, auger or skid steer rental, permit fees, and fuel for a long drive all go here.
Step 5: Add overhead
Take your yearly overhead and divide it by the crew hours you sold last year. That gives an overhead rate per crew hour. Multiply it by this job's hours.
Step 6: Set the price from your target margin
Add materials, labor, job costs and overhead. Divide by one minus your target margin. Round to a clean number.
Step 7: Turn it into a per foot price and line items
Divide the base fence price by the linear feet for a per foot rate. Show gates and extras as separate lines so the homeowner can see what changes the total.
What does a worked example look like?
These are example numbers, not market prices. Use your own costs.
The job: 150 linear feet of 6 foot wood privacy fence with one 4 foot walk gate, flat yard, no old fence to remove.
| Line | How it is figured | Example amount |
|---|---|---|
| Materials | Posts, rails, pickets, concrete, hardware, gate kit, waste | $3,300 |
| Labor | 2 person crew, 2 days, 32 crew hours at $40 loaded cost | $1,280 |
| Job costs | Auger rental and fuel | $250 |
| Overhead | 32 crew hours at $25 per hour | $800 |
| Total cost | $5,630 | |
| Price at a 30% margin | $5,630 divided by 0.70, rounded | $8,050 |
$8,050 divided by 150 feet is about $53.67 a foot with the gate included. If you quote the gate as its own line, take its cost out first and work the per foot rate from what is left.
Now change one thing. Say the same yard has rock and you lose a full day to the bar and the jackhammer. That is 16 more crew hours: $640 in labor and $400 in overhead. Your cost goes to $6,670. If you kept the $8,050 price, your margin falls from 30% to about 17%. That is why rock, slope and removal need their own lines.
Which extras should you price as separate lines?
Fence jobs vary more than most trades because the ground varies. Keep the per foot rate for plain runs and price the rest as add-ons.
| Item | Why it is separate | How to price it |
|---|---|---|
| Walk gates and drive gates | Heavier posts, hardware, more hours | Per gate, by size |
| Old fence removal and haul-off | Labor plus dump fees | Per foot, plus a disposal line |
| Rock or hard digging | Can double hole time | A per hole add-on, or a written allowance |
| Slope or stepped panels | Extra cuts and layout time | A percent on the affected run |
| Permit and HOA paperwork | Office time and fees | Fee plus your admin time |
| Stain or sealer on wood | Extra trip and material | Per foot or a flat line |
| Long drive | Fuel and lost crew time | A travel charge past a set radius |
For the travel line, the IRS business standard mileage rate was 76 cents a mile for July to December 2026 (IRS: Standard mileage rates (2026)). You can use that as a simple check on what a mile of truck costs, though your real cost may be higher with a loaded trailer.
Does the type of fence change how you price it?
The method stays the same. The inputs change.
- Wood privacy is material heavy and labor heavy. Pickets go on one by one.
- Vinyl has higher material cost per foot but panels go up fast. Hours drop, materials rise.
- Chain link has lower material cost and needs a stretcher and tension work. Price the terminal posts carefully.
- Aluminum and ornamental are panel systems with precise post spacing. Slopes take extra time.
Track hours by fence type. After one season you will know your real feet per crew day for each, and your bids get faster and more accurate. Estimating apps can help with takeoffs and line items. See our guide to fence estimating software for a side by side look.
Should you show fence prices online?
Many homeowners want a ballpark before they book a visit. A "starting at" price per foot for a plain run, with a clear note that gates, removal and ground change the total, can filter out tire kickers. Our guide on whether fence companies should show prices online covers the trade-offs. If you want to collect yard details before you drive out, read about online quote forms for fence companies.
When should you raise your fence prices?
Check your numbers at least once a year, and any time a supplier raises prices. If spring is your busy season, set next year's rates before it starts. If your calendar is full weeks out and you win most bids, your price may be too low. If you lose most bids, look at how you present the quote before you cut the price. Our guide on seasonal marketing for fence companies helps fill the slower months so you do not discount to stay busy.
Permit and licensing rules also differ by state and town, and they can add fees and office time to a bid. Check your own state, such as our Texas fence company page, and your town's building office.
What else affects whether your price wins the job?
Price is only part of the decision. A fast reply, a clear written quote and proof of past fences all help a homeowner say yes to a fair number. The hub guide on how contractors get more leads covers the wider picture. A website that shows your fence types, gates and service area does a lot of that selling before you arrive. If you want to see one built for fence companies, see a free demo site.
Common questions
How much profit should a fence company make on a job?
There is no single right number, and we have not found a public source that gives one for fence companies. Pick a target margin that covers your slow months, equipment and growth, then price every job to it. Track the real margin after each job so you know if the target holds.
Should I price fences per foot or per job?
Use both. Build the price for the whole job from your costs, then show a per foot rate for the plain run so the homeowner can compare. Keep gates, removal and hard digging as separate lines.
How do I price fence removal?
Price it from the hours it takes your crew plus the dump or haul-off cost. Removal varies with post depth and concrete, so look before you quote. Show it as its own line so the homeowner sees it.
What if the material price goes up after I quote?
Put an expiry date on every quote, such as 30 days, and say the price holds until then. If the homeowner signs after it expires, reprice the materials. Telling them up front avoids an awkward call later.
Do I need to call 811 for every fence job?
The 811 service lists installing fences as a job where you should contact 811 a few business days before digging. It is free. Build that wait into your schedule and your start date.
Sources
- BLS: Employer Costs for Employee Compensation, Table 4 (2026)
- BLS: Employer Costs for Employee Compensation news release (2026)
- IRS: Self-employment tax (Social Security and Medicare taxes) (2026)
- IRS: Standard mileage rates (2026)
- 811: Before you dig (2026)
We build your new website free, before you pay, then work every week to get you named when homeowners ask Google and AI who to call. Get your free demo site.